2015年5月信息系统项目管理师综合知识真题详解 71-75题

2015-07-06 22:26 309 查看
71、wireless LAN,also widely known as WLAN or WIFI,is probably the most well-known member of the IEEE802 protocol family for home users today.It is standardized by()and shares many properties with wired Ethernet .

A、IEEE 802.1

B、IEEE 802.3

C、IEEE 802.5

D、IEEE 802.11

“我能过软考”解析:

无线局域网,被广泛称之为WLAN或WIFI,是人们最为熟悉的IEEE802协议族。它由()协议定义标准并具备许多有限局域网的特性

参考答案: D

72、When multiple routers are used in interconnected networks,the routers exchange information about()using a dynamic routing protocol .

A、destination addresses

B、IP addresses

C、work addresses

D、router addresses

“我能过软考”解析:

当接入网络存在多个路由器时,路由器利用动态路由协议交换()信息

A、目的地址

B、IP地址

C、工作地址

D、路由地址

参考答案: A

73、Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resource.

A、work breakdown structure

B、baseline

C、software requirements specification

D、plan

“我能过软考”解析:

制定项目进度计划之前,制定计划者需要()、各任务的工作量估计以及可能得到的资源列表

A、分解结构

B、基线

C、软件需求描述

D、计划

参考答案: A

74、Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an element .

A、relationships

B、resources

C、stakeholders

D、deliverables

“我能过软考”解析:

建立项目管理的时间表需要里程碑列表、各活动、以及含有估计开始和结束时间的(),其中员工的调度被看作为元素。

A、关系

B、资源

C、干系人

D、可交付物

参考答案: D

75、The following diagram denotes dependency between two activities A and B,It says()



A、B can’t start before A is finished

B、B can’t finish before A is finished

C、B can’t start before A starts

D、B can’t finish before A starts

“我能过软考”解析:

下图表示的活动A与B的依赖关系可以描述为()

A、A结束前B不能开始

B、A结束前B不能结束

C、A开始前B不能开始

D、A开始前B不能结束

参考答案: A